1). Difference between Calendar Days and Work Days
Don’t people already know this? Well seems like “Not everybody!”
Both seasoned IT entrepreneurs as well as developers make this common mistake. They don’t seem to quite understand the difference between calendar days and work days. So let me ask you this question – “What should be the delivery date of a project starting on October 1st and having an estimated effort of 160 hours?”
A typical calculation goes like this:
160 hrs / 8 hrs per day = 20 days.